Power cuts: Tegbe says first units back within 72 hours as TCN disputes Ikeja Electric
The power minister blames Egbin maintenance, gas shortages and sabotage, and says the first units return within 72 hours. TCN rejects Ikeja Electric's account of Band A outages.
By John Christian Mmaduabuchi, Chief Editor
· · Video · Lagos

The gist in 30 seconds
- The Minister of Power, Joseph Tegbe, said in a statement on Friday, 6 November 2026, that the first affected generating units should return to service within 48 to 72 hours.
- He blamed the outages on planned maintenance at Egbin Power Station, gas supply constraints at some thermal plants and sabotage of key transmission lines.
- TCN said on Friday, 6 November 2026, that Ikeja Electric's claim that grid instability caused outages on its Band A feeders was inaccurate, blaming low generation instead.
Updated 09:23 WAT, 10 Nov 2026: Tegbe said on Monday that power had been restored to many of the affected areas and that Egbin’s first turbine was back in service, though some places were still without supply.
The Minister of Power, Joseph Tegbe, has said the first of the generating units behind this week’s power cuts should be back in service within 48 to 72 hours. He blamed the outages on planned maintenance at Egbin Power Station in Lagos, gas shortages at some thermal plants and sabotage of transmission lines.
His statement, titled “Update on Power Situation” and posted on his social media pages on Friday, 6 November 2026, came on the same day the Transmission Company of Nigeria (TCN) publicly rejected Ikeja Electric’s explanation for outages on its Band A feeders.
Why it matters
Homes and businesses in Lagos, Abuja and other cities have had far fewer hours of grid power this week, pushing many back on to generators while petrol prices stay high and the dry season heat sets in. By Monday, 9 November, the minister said supply had been restored to many of the affected areas, though not all of them. The latest is under What happens next below.
What the minister said
“I am aware of the strain that the current outages have placed on households and businesses in four affected states, including Lagos and the Federal Capital Territory,” Mr Tegbe said.
He said planned maintenance at Egbin, which he described as Nigeria’s largest thermal power station and the source of about 16% of the electricity supplied to the national grid, together with gas constraints at some thermal stations, had reduced the power available on the grid. “Grid operators have, therefore, implemented load shedding in some areas to manage the shortfall,” he said. Sabotage of key transmission lines, he added, had limited the use of other routes to supply some areas, especially Lagos.
“My team and I are working to return the affected generating units to service in phases, with the first units coming back online within the next 48 to 72 hours,” the minister said. The ministry was also working with operators to improve gas supply and speed up repairs to damaged infrastructure, he said.
Why are TCN and Ikeja Electric at odds?
Ikeja Electric published notices on Wednesday, Thursday and Friday apologising to customers on some Band A feeders, in areas including Ogba, Ikeja GRA, Maryland, Opebi, Ogudu, Alausa, Ilupeju and Gbagada, for missing the minimum of 20 hours of supply a day between 2 and 5 November. In several of the notices it blamed grid instability, Premium Times reports.
In a statement on X on Friday, TCN described that explanation as inaccurate and misleading. It said that under section 67 of the Electricity Act 2023, only the Nigerian Independent System Operator (NISO) can determine the causes of disturbances and shortfalls on the grid, and that NISO had not blamed TCN for these outages. “TCN can only transmit the energy made available to it and cannot transmit energy that is not generated,” the company said.
Citing records of feeder interruptions on 1 and 2 November, TCN said 68% of the load shedding came from low generation and frequency control on the grid. It put 26% down to Ikeja Electric not keeping to its load allocations from NISO’s National Control Centre, and to faults and maintenance on the distribution company’s own network, and the remaining 6% to its own planned maintenance, switching and line limits.
No public response from Ikeja Electric to TCN’s statement had been reported by 10:56 WAT on Saturday, 7 November.
What does this mean for Band A customers?
Ikeja Electric’s notices are what the Nigerian Electricity Regulatory Commission (NERC) requires. Under its 2024 order on service commitments, a distribution company that misses the promised hours on a Band A feeder for two days in a row must publish an explanation and say when normal service will return. If a feeder falls short for seven days in a row, it must be moved to the band that matches the supply it actually received, which means a lower tariff. Our guide to what your band entitles you to explains the rules.
A GistMatrix reading of TCN’s own figures shows that, by its account, about two-thirds of the load shedding it recorded came from a shortage of power to share rather than from faults on either company’s network. That is why the return of the affected generating units and more gas for thermal plants, more than local repairs, will decide when the lights stay on longer.
What happens next
On Monday, 9 November, Mr Tegbe said in an update on his Facebook page that power had been restored to many of the areas affected in Lagos, Ogun, Oyo, Kwara and the Federal Capital Territory. He said the vandalised Benin–Egbin 330kV transmission line had been repaired, taking supply to the Lagos area of the grid above 1,000 megawatts (MW), and acknowledged that some locations were still without power, Daily Trust and Vanguard reported.
Speaking on TVC’s The Morning Brief the same day, he apologised to Nigerians, said the outages were not a national grid collapse, and said Egbin’s ST1 turbine was back in operation, with a second turbine, ST3, due to return later on Monday and add about 150MW, Premium Times reported. He also said the Oshogbo–Ikeja West line, out of service for more than 18 months, should be restored by the end of November, adding about 400MW for Lagos.
Generation on the national grid stood at 4,020.41MW at 1pm on Monday, below Sunday’s peak of 4,253.6MW, according to NISO data reported by Vanguard, which said the rise had yet to translate into adequate supply for many consumers. Egbin, with an installed capacity of 1,320MW, was producing 108MW.
Watch for ST3 and Egbin’s other units to return, for NISO’s daily generation figures, and for whether Ikeja Electric’s Band A feeders return to 20 hours a day before NERC’s seven-day downgrade rule comes into play. No public response from Ikeja Electric to TCN’s statement had been reported by Tuesday morning, 10 November. Our guide to what Band A customers are owed has the rules on compensation and downgrades.
Is your feeder getting its band’s hours yet? Tell GistMatrix which DisCo supplies you and how many hours of power you are getting.
Sources
We checked this story against these sources. How we check
- Premium Times: Power minister explains recent nationwide outages (Joseph Tegbe statement) (7 Nov 2026)
- Nairametrics: Tegbe says electricity supply to improve within 72 hours as FG tackles grid constraints ("Update on Power Situation" statement) (7 Nov 2026)
- Premium Times: TCN disputes Ikeja Electric's reason for power outages on Band A feeders (TCN statement on X) (7 Nov 2026)
- Nairametrics: TCN accuses Ikeja Electric of misleading customers over feeder outages (TCN statement) (6 Nov 2026)
- Technext: Persistent Lagos power outages: Ikeja Electric blames reduced grid allocation (Ikeja Electric notices) (7 Nov 2026)
- Leadership: NERC orders automatic downgrade after 7 days non-performance (MYTO 2024 supplementary order) (5 Apr 2024)
- Daily Trust: Minister: Power Restored To Many Areas Hit By Outage (Joseph Tegbe update on Facebook) (9 Nov 2026)
- Premium Times: Power minister apologises to Nigerians over outages, promises improved electricity supply (Joseph Tegbe on TVC's The Morning Brief) (9 Nov 2026)